Xuan Thanh Cement Plant is invested by Xuan Thanh Group, is located in Thanh Nghi Commune, Thanh Liem District, Ha Nam Province. This is the second production line that Lilama 69-3 performs as a general contractor for fabrication and installation. The contract implementation progress is shortened and the project implementation process is always monitored and appreciated by the Investor and FLSmidth supervisors, thereby affirming the capacity and reputation in the field of manufacturing and installation of industrial plants by ensuring safety, quality and schedule.
Preparation for craning the Clinker Kiln by a 600-ton-crawler-crane, Demag CC2800
Large items with crane weighing more than 320 tons
Perf of Closure craning on 12/7/2022, complete the installation of Clinker Kiln with a capacity of 12,500 tons clinker/day
Technical parameters
Furnace length: 97,7m
Furnace diameter: 6,4m
Total weight: 2.000 tấn
2.
"Speed up" the project progress: This is one of the items in the project of manufacturing and installing a Lime Kiln with a capacity of 500 tons/day, at Hoa Phat Iron and Steel Complex with manufacturing and installation volume nearly 3,000 tons. The kiln height is 66m with the implementation duration is 3.5 months. The project is on the way of completing and handing over to the Investor ensured on schedule and quality.
Final steps of completion of Installation Lime Kiln in Hoa Phat Iron and Steel Complex - Kinh Mon, Hai Duong.
3. Continued to be trusted and selected by the Investor: With many years of experience in the field of manufacturing and installing mechanical equipment, Lilama 69-3 was awarded the contract by Chinfon Cement Company to "Supplying materials, fabrication, dismantling and installing equipment for upgrading the combustion chamber and Cyclones of drying tower No.2 of Chinfon Cement Plant" with the volume of fabrication and installation of more than 4000 tons, the lead time is 107 days. This is an important contract marking the determination of employees of Lilama 69-3 JSC., in completing and meeting the Investor's required schedule.
Drawing of renovation and upgrade of the combustion chamber and Cyclones of Drying Tower No. 2 Chinfon Cement Factory