Three major domestic projects, important highlights in 2022.

Friday - 29/07/2022 10:02
1. Ahead of schedule, ensuring Safety - Quality for "Heart of the factory": This is the item of Clinker Kiln Line No.3, Xuan Thanh Cement Plant with a capacity of 12,500 tons of Clinker/day which is used FLSmidth technology, fabricated and installed by Lilama 69- 3.
Xuan Thanh Cement Plant is invested by Xuan Thanh Group, is located in Thanh Nghi Commune, Thanh Liem District, Ha Nam Province. This is the second production line that Lilama 69-3 performs as a general contractor for fabrication and installation. The contract implementation progress is shortened and the project implementation process is always monitored and appreciated by the Investor and FLSmidth supervisors, thereby affirming the capacity and reputation in the field of manufacturing and installation of industrial plants by ensuring safety, quality and schedule.
1
Preparation for craning the Clinker Kiln by a 600-ton-crawler-crane, Demag CC2800
3
Large items with crane weighing more than 320 tons
4
Perf of Closure craning on 12/7/2022, complete the installation of Clinker Kiln with a capacity of 12,500 tons clinker/day

Technical parameters
Furnace length: 97,7m
Furnace diameter: 6,4m
Total weight: 2.000 tấn


2. "Speed up" the project progress: This is one of the items in the project of manufacturing and installing a Lime Kiln with a capacity of 500 tons/day, at Hoa Phat Iron and Steel Complex with manufacturing and installation volume nearly 3,000 tons. The kiln height is 66m with the implementation duration is 3.5 months. The project is on the way of completing and handing over to the Investor ensured on schedule and quality.
5

Final steps of completion of Installation Lime Kiln in Hoa Phat Iron and Steel Complex - Kinh Mon, Hai Duong.

3. Continued to be trusted and selected by the Investor: With many years of experience in the field of manufacturing and installing mechanical equipment, Lilama 69-3 was awarded the contract by Chinfon Cement Company to "Supplying materials, fabrication, dismantling and installing equipment for upgrading the combustion chamber and Cyclones of drying tower No.2 of Chinfon Cement Plant" with the volume of fabrication and installation of more than 4000 tons, the lead time is 107 days. This is an important contract marking the determination of employees of Lilama 69-3 JSC., in completing and meeting the Investor's required schedule.
6

Drawing of renovation and upgrade of the combustion chamber and Cyclones of Drying Tower No. 2 Chinfon Cement Factory



 

Total notes of this article: 0 in 0 rating

Click on stars to rate this article

  Reader Comments

Catid
Developing export markets and diversify mechanical products.
This is one of the important contents directed by the Company's General Director in the briefing meeting at the end of 2023. Identifying mechanical...
Lilama 69-3 has completed many projects to ensure "PROGRESS - SAFETY - QUALITY" through 2022.
With the goal of speeding up the implementation of projects, focusing on exploiting strengths in processing, manufacturing, installing mechanical...
Three major domestic projects, important highlights in 2022.
1. Ahead of schedule, ensuring Safety - Quality for "Heart of the factory": This is the item of Clinker Kiln Line No.3, Xuan Thanh Cement Plant with a...
ACCELERATION OF THE PROGRESS OF LOCAL  PROJECTS AND  EXPORT PROJECTS IN 2022.
To ensure the completion of projects in accordance with the 2022 plan and the progress of the projects.
You did not use the site, Click here to remain logged. Timeout: 60 second